Section 3 · Project Scheduling

2 min read
On this page 6 headings

Why a schedule matters: a schedule helps the project manager monitor the timely completion of each task, and take corrective action if the project falls behind.

The eight scheduling activities

#Activity
1Identify major activities
2Break activities into tasks
3Determine dependencies
4Estimate each task’s duration
5Represent tasks in a diagram
6Assign start and end dates
7Find the critical path
8Allocate resources
Figure 16. The eight principal steps of project scheduling.
Figure 16. The eight principal steps of project scheduling.
Open image ↗
Illustration: Section 3 · Project Scheduling

Work Breakdown Structure (WBS)

The root is the project. Each node is broken into children; each leaf is a task that can be allocated to a developer and scheduled, roughly two weeks of work.

Seller Portal WBS

The Seller Portal is broken into Requirement Gathering and Analysis, Design and Development. Requirements includes gathering requirements and creating an SRS. Design includes the component diagram, database schema and user interface. Development includes catalogue management, inventory management and order tracking.

Seller Portal WBS.
Seller Portal WBS.
Open image ↗
Seller Portal WBS.

From WBS to activity network

Leaf nodes of the WBS become nodes of the activity network. The activity network shows dependencies and durations of tasks.

WBS leaf nodes become activity network nodes: dependencies are shown here; Figure 20 and the table add task durations.
WBS leaf nodes become activity network nodes: dependencies are shown here; Figure 20 and the table add task durations.
Open image ↗
WBS leaf nodes become activity network nodes.
TaskDuration (days)
Component diagram15
User interface30
Database schema10
Catalogue management15
Inventory management15
Order tracking25
Payment tracking40
Sales tracking30
Customer feedback30
Figure 20. The lecture’s nine-task Seller Portal dependency network.
Figure 20. The lecture’s nine-task Seller Portal dependency network.
Open image ↗
Illustration: Section 3 · Project Scheduling

Gantt chart

A special type of bar chart: each bar is an activity, its length proportional to the planned duration. In the Seller Portal, user interface and database schema start together (UI takes longer); catalogue, inventory and order tracking happen one after the other; then payment, sales and customer feedback happen in parallel.

Seller Portal Gantt chart (days).
Seller Portal Gantt chart (days).
Open image ↗
Seller Portal Gantt chart (days).

Representations like the Gantt chart help all members of the team be aware of the schedule.

Critical path

The critical path is a chain of tasks that determines the duration of the project.